A contractor agreed to construct a 6 km road in 200 days. He employed 140 persons for the work. After 60 days, he realized
that only 1.5 km road has been completed. How many additional people would he need to employ in order to finish the work
exactly on time? (in numerical value)

Correct answer: 40