CAT 2022 · Slot 3 Quant Question 7
A group of N people finished 35% of a project by working 7 hours a day for 10 days. Then 10 people left and the rest finished the remaining 65% in 14 days at 10 hours a day. The value of N is
- 150
- 23
- 36
- 140
Correct answer: D · 140