CAT 2023 · Slot 3 Quant Question 16

Gautam and Suhani together finish a job in 20 days. If Gautam does only 60% of his usual work on a day, Suhani must do 150% of her usual work that day to exactly make up for it. The number of days required by the faster worker alone is

Correct answer: 36